Can Europe pull off the world’s most ambitious energy project? 

As the world moves towards its shared climate change ambitions, a “step-change” could be coming for Europe’s energy systems. Andrew Tunnicliffe learns about the North Sea Wind Power Hub programme, the challenges it faces, and the rewards if it can overcome them.

“Ambitious”, “innovative”, and “world-leading” are all words we have become familiar with, particularly in business. We often see them attached to a statement about a new partnership, project, or product set to “reshape the landscape”. They do, however, often have a close association with a word less commonly used: “challenging”.


One project boasting ambition and challenge in equal measure is the North Sea Wind Power Hub (NSWPH), currently under consideration by a cross-European consortium comprising Transmission System Operators – TenneT (the Netherlands and Germany), Energinet (Denmark), and Gasunie (the Netherlands). Their aim is to develop multiple hub-and-spoke projects in the North Sea to facilitate producing a significant amount of the continent’s sustainable energy from North Sea offshore wind, helping Europe meet its obligations under the Paris Agreement.

/ By 2045, with the addition of other hubs, the project could be supplying 180GW across the European Union. /

What is a hub-and-spoke wind project?

TenneT’s Dutch-based project manager, Michiel Müller, says the consortium came together to proactively consider an approach to the large scale offshore wind roll-out required to combat climate change, but one that is both secure and affordable.


“In July 2019 we shared the result of the broad assessment phase, which concluded that the hub-and-spoke concept is both technically and economically feasible,” he says.


Hub-and-spoke infrastructure, in this context, involves wind farms connected to islands (the hubs), where electricity is converted from AC to DC before being distributed to connecting regions and countries (the spokes); a process, Müller adds, that requires a step-wise approach. In addition to powering homes and businesses directly, some of the energy produced will be converted to gas for use or storage.

/ By 2045, with the addition of other hubs, the project could be supplying 180GW across the European Union. /

On this scale, he explains, this project is the first of its kind: “There is currently really no comparable project out there. The closest is the Kriegers-Flak project, which does have a hybrid asset functionality: providing both grid connection and interconnection.”


On completion, which is currently expected to be around the early 2030s, the hub will operate at around 10–16GW capacity. By 2045, with the addition of other hubs, the project could be supplying 180GW across the European Union according to the group. Currently, although a location has not yet been identified, the consortium is undertaking preparatory work to better understand both the long-term roll-out and initial first stage of the project.

/ To meet the climate goals we need to considerably increase our rate of deployment. /

Great challenge calls for great collaboration

However, as with all big ambitions the project is not short of challenges, which Müller is keenly aware of. Except these obstacles have little to do with technology.


“Of course many of the challenges come with the sheer scale of the project, which is unprecedented… Likely, however, the biggest challenges are not on the technical side, but rather in finding a way to orchestrate this, cross-border, in a strongly internationally coordinated way. It really is a step-change compared to ‘business as usual’.”


The questions raised are significant, not just in the context of international collaboration but in the shadow of what will likely be a difficult economic period following recent events. Müller says that among the issues will be: how are the bidding zones organised when large scale offshore enters the system through hybrid assets; how would cross-border cost allocation work; and how are cross-energy sector projects from a societal cost–benefit perspective assessed?

/ To meet the climate goals we need to considerably increase our rate of deployment. /

“We are currently in the process of identifying the topics that need to be analysed and discussed in detail, as well as any potential regulatory barriers that need to be considered,” he says. “It is important that the respective governments find ways to work closely together towards concrete projects, while at the same time structured dialogues are being created with the relevant stakeholders to develop the market and regulatory frameworks that support the development.”


With a lead time of around a decade, Müller urges governments to act now if this project, or others like it, were to have a chance of meeting climate change goals. Speaking specifically of the NSWPH, he says that action needed to be taken soon if the early 2030s target was to be achieved, adding that involved governments “need to take decisions in the coming years”.


“To meet the climate goals we need to considerably increase our rate of deployment and find new ways to integrate this into the energy system. We should also realise that these types of projects generally take around 10 years to build, while we only have 30 years to complete it all,” he warns.

Image: NSWPH

/ Current policies, market design, and regulatory framework should be urgently reconsidered. /

The Brexit–North Sea connection

Another issue the project has faced is the fast-approaching UK and European Union cliff edge. Brexit, often forgotten about among recent headlines, has already had an impact according to Nico Van Dooran, director of new business at the Port of Rotterdam (a strategic partner of the NSWPH consortium). He told attendees of a virtual conference at the beginning of July, hosted by Aberdeen’s Oil and Gas Technology Centre, that the political situation had filtered down and hindered the project.


“We have been trying to get the British energy industry involved but Brexit was really getting in the way of all these developments,” he said. “But I think we should continue and share our knowledge on both sides.”


It’s a view shared by Müller: “We believe it is really important that we find a way to work closely with the UK. There is a lot of value in connecting the energy markets and, moreover, the UK's offshore wind ambition is very much aligned with that of Europe; there is great potential for synergies.”

/ Current policies, market design, and regulatory framework should be urgently reconsidered. /

However, by the beginning of July Van Dooran said that although there was some contact with UK-based partners, it was not frequent enough to have an impact: “We are aware of some of the projects that are going on in the UK… But I think we can share more and develop more together.”


When the project was first mooted, with the expectation that the UK would have been more forthcoming, the consortium’s 2019 report had already highlighted the hurdles any success would have to overcome.


“Current policies, market design, and regulatory framework should be urgently reconsidered to enable the successful development of multiple hub-and-spoke projects towards 2050,” it said.

/ Significant changes were required in national practices, approaches, planning, and policies to allow for integrated infrastructure projects. /

Energy sustainability means a new approach

The report added that while it is possible to build a first hub-and-spoke project within the current regulatory framework and market design, significant changes were required in national practices, approaches, planning, and policies to allow for integrated infrastructure projects such as the modular hub concept to become part of the long-term energy transition.


“We are convinced that this massive challenge requires a change in our approach to connecting offshore wind,” Müller continues.

/ Significant changes were required in national practices, approaches, planning, and policies to allow for integrated infrastructure projects. /

He believes that instead of a national incremental focus, with radial connection of offshore wind and uncorrelated point-to-point interconnections, an international coordinated approach that maximises synergies and the use of the North Sea energy resource, along with connecting energy markets, is essential.


He adds it should be hybrid, combining grid connection and interconnection functionality to minimise infrastructure cost, and be across energy sectors to provide the required large scale flexibility to the system required to ensure security of supply.

/ We aim to provide a grid connection concept which maximises socio-economic welfare while providing the security of supply. /

NSWPH – a project worth the challenge

Every major infrastructure project has its challenges; this one, however, might have more than its fair share given the current climate. The mantra that nothing is worth doing if it isn’t a challenge is true here though, at least that is the hope. There are several major issues facing Europe in coming decades with the scaling back of coal mining and Germany’s decision to cut its use of nuclear power.


For this reason it can be argued the challenge is worthwhile.

/ We aim to provide a grid connection concept which maximises socio-economic welfare while providing the security of supply. /

“We approach this from a social-economic welfare perspective. Given the political and societal ambitions with respect to the roll-out of offshore wind, we aim to provide a grid connection concept which maximises socio-economic welfare while providing the security of supply as we know it today,” says Müller.


For now, analysis continues, discussions are ongoing and the project awaits the next move from regulators, whilst it continues its work. There will likely not be an initiative of this kind, with this unique backdrop, again. If it can be got right, the future of sustainable power for Europe has huge promise.

Playing catch-up in the US

“In Europe, offshore wind has been there for a number of years, but I think in the United States we're a little bit behind that,” said Karustis.


Should it be successful, Halo’s approach could lead to a surge in US onshore wind, which has historically lagged behind other regions in terms of wind installation and production. Since 2016, according to the International Energy Agency, the US has installed just 22.6GW of new onshore wind capacity, compared to 30.7GW in the EU, and 50.3GW in China, struggles that Karustis hopes to address.


Last December, the Chinese Government approved a number of new offshore wind projects, totalling 13GW of production and costing around $13.3bn, as the country continues to invest in utility-scale power. Karustis hopes projects like Halo’s distributed turbine can contribute to a more balanced wind sector in the US, with both large- and small-scale operations expanding renewable power.


“The large-scale wind turbines wouldn't be phased out, it's kind of an ‘all of the above’ thing,” he said. “The large wind farms play a very important role for us in reducing the carbon footprint globally, and hopefully the micro wind market is going to augment that by producing energy where energy is being used. It's a good two-pronged approach.”


This two-pronged approach also includes other renewable power sources, including solar and utility-scale wind; Halo is not trying to replace all clean energy with its turbines, but offer another option for people eager to engage in renewable power, who may have been historically sidelined due to the high costs of building utility-scale facilities or the unsuitable geographical characteristics of the places they live.


“When you look at that market we're very excited because just as megawatt-scale wind is a large market, I think distributed wind can be as big of a market or bigger over time,” said Karustis.


“When you have incentives and improvements in the technology, the costs go down, so you can be more competitive and compete, and that's certainly the case with megawatt-scale wind,” he continued. “Just 15/20 years ago, it wasn't competitive with natural gas [and] coal, but it is now. So those government policies have helped and they've driven the technology improvements, so it's all bundled together.”